DDOT Street Construction Project  
Street Construction Detail for U St

Field Value
STREET NAME: U St
QUADRANT: NW
FROM INTERSECTION: 9th St, Florida Ave (E)
TO INTERSECTION: Florida Ave (W)
WARD: 1 and 2
FUNCTIONAL CLASS: PRINCIPAL ARTERIAL
NUMBER OF BLOCKS: 10
MILES: .93
WORK DESCRIPTION: Design
Field Value
STATUS: Active Design
ACTUAL START DATE: 10/9/2006
ESTIMATED COMPLETION DATE: 8/29/2008
YEAR BUDGETED: 2006
FEDERAL COST: $0
DC COST: $0
TOTAL COST: $0
PERCENT COMPLETED: 95%
COMMENTS:
 
Contact Webmaster